Current Massing Studies
The School Building Committee is currently considering six massing studies. One of these conceptual designs will be recommended to the Massachusetts School Building Authority (MSBA) to for progression into the next phase of the project, Schematic Design.
What are massing studies?
Massing studies are conceptual diagrams created based on the high-level requirements of a project. These studies illustrate the potential locations and dimensions of a project. Massing studies do not represent final designs, locations, or costs associated with a project.
This graphic outlines the six massing studies under consideration by the School Building Committee in the Preferred Schematic Report. One option will be moved into Schematic Design.
These massing studies are purely conceptual and do not represent final costs, locations, or designs.
B. Renovation & Addition
B.1 Quad
Project Cost: $636M
Construction Duration: 5 Years
Floors: 2-4
Building Location: Existing Footprint
B.4 Figure Eight
Project Cost: TBD
Construction Duration: 6 Years
Floors: 2-3
Building Location: Existing Footprint
C. New Construction - On fields
C.1d Branch
Project Cost: $595M
Construction Duration: 4 Years
Floors: 4
Building Location: Fields
C.2b Braid
Project Cost: $598M
Construction Duration: 4 Years
Floors: 4
Building Location: Fields
C.5b Bloom
(Revised 9/16)
Project Cost: $591M
Construction Duration: 4 Years
Floors: 4
Building Location: Fields
D. New Construction — Phased-in-place
D.2 Weave
Project Cost: $621M
Construction Duration: 5 Years
Floors: 4
Building Location: Existing Footprint