Current Massing Studies

The School Building Committee is currently considering six massing studies. One of these conceptual designs will be recommended to the Massachusetts School Building Authority (MSBA) to for progression into the next phase of the project, Schematic Design.

What are massing studies?

Massing studies are conceptual diagrams created based on the high-level requirements of a project. These studies illustrate the potential locations and dimensions of a project. Massing studies do not represent final designs, locations, or costs associated with a project.


This graphic outlines the six massing studies under consideration by the School Building Committee in the Preferred Schematic Report. One option will be moved into Schematic Design.

These massing studies are purely conceptual and do not represent final costs, locations, or designs.

B. Renovation & Addition

B.1 Quad

Project Cost: $636M

Construction Duration: 5 Years

Floors: 2-4

Building Location: Existing Footprint

Pros, Cons, and Details of B.1 Quad

B.4 Figure Eight

Project Cost: TBD

Construction Duration: 6 Years

Floors: 2-3

Building Location: Existing Footprint

Pros, Cons, and Details of B.4 Figure Eight

C. New Construction - On fields

C.1d Branch

Project Cost: $595M

Construction Duration: 4 Years

Floors: 4

Building Location: Fields

Pros, Cons, and Details of C.1d Branch

C.2b Braid

Project Cost: $598M

Construction Duration: 4 Years

Floors: 4

Building Location: Fields

Pros, Cons, and Details of C.2b Braid

C.5b Bloom
(Revised 9/16)

Project Cost: $591M

Construction Duration: 4 Years

Floors: 4

Building Location: Fields

Pros, Cons, and Details of C.5b Bloom

D. New Construction — Phased-in-place

D.2 Weave

Project Cost: $621M

Construction Duration: 5 Years

Floors: 4

Building Location: Existing Footprint

Pros, Cons, and Details of D.2 Weave